Autorizzazione Unica: quali sono gli impianti esenti?

As it was not fully implemented the directive of the Legislative Decree 387/2003 that provided for the exemption from 'One Authorization for plants built at sites without constraints and for which it is required by local authorities (Municipality, Province, Region) the issue of special authorizations provided for under the current regulations regarding the protection environment, protection of landscape and historical and artistic heritage, the facilities on the ground must be subject to proceedings for a single authorization even if built on sites without constraints. E 'was also expected to attend the Conference of representatives of the MBAC Services even if there are specific constraints, and the person responsible, in case of submission of application for a single authorization, it must make a statement to the competent Superintendents to verify the existence of proceedings or the protection of procedures for ascertaining the existence of archaeological heritage.

are exempt from the process for a single authorization and are subject to communication to the local City Hall PV:

  • attached to or integrated in the roofs of existing buildings con la stessa inclinazione e lo stesso orientamento della falda e i cui componenti non modificano la sagoma degli edifici;
  • realizzati su edifici esistenti aventi una capacità di generazione compatibile con il regime di scambio sul posto . 
Sono esenti dal procedimento di Autorizzazione Unica e sono soggetti alla DIA (Dichiarazione di Inizio Attività) recentemente sostituita dalla SCIA (Segnalazione Certificata di Inizio Attività) gli impianti fotovoltaici:

  • con potenza inferiore a 20 kW anche in presenza di vincoli;
  • realizzati su edifici esistenti differenti da quelli del precedente comma.
Sono soggetti al procedimento di Autorizzazione Unica gli impianti:

  • costruiti in siti per i quali sia richiesto dall'autorità locale (Comune, Provincia, Regione) il rilascio di specifiche autorizzazioni, previste dalle normative vigenti in materia di tutela dell'ambiente, di tutela del paesaggio e del patrimonio storico-artistico;
  • da installare su edifici in costruzione con inclinazione e orientamento diversi rispetto a quelli della falda;
  • da installare sul terreno.
Ecco quale documentazione deve presentare alla Regione il Soggetto Responsabile insieme all'istanza di rilascio dell'Autorizzazione Unica:

  • progetto definito;
  • report technical documentation available
  • area;
  • STMG prior connection or network operator;
  • certificate of urban destination;
  • receipt for payment of charges instructors
  • commitment to security to ensure that interventions disposals;
  • occurs via soggettibilità where required;
  • copy communication in supervision.
What are the sequences of the single procedure?

The legislature has provided the following deadlines for the performance of the procedure carried out only:

  • within 15 days from the date of submission of Administration shall verify the completeness of formal documentation and communicates the commencement of proceedings;
  • within 30 days from the date of submission of the administrative department shall convene the Conference of the Services;
  • within 90 days from the date of submission of 'instance of the administrative department requires additional documentation if necessary;
  • within 30 days of the request for additional documentation to the Responsible Party shall provide additional documentation;
  • within 180 days from the date of submission of the administrative authorities would find the authorization procedure single sentence compensation for harm caused by the failure to conclude.
single license:

  • supersedes any act of competence of the administrations involved;
  • is entitled to construct and operate the photovoltaic and associated works and variations to planning instrument where appropriate, includes any
  • requirements for the construction and operation of the photovoltaic system and defines the means to restore the condition of the premises;
  • determine compensatory measures for environmental and territorial expected date for start and completion of the work of installation of the expiration of the such as single license lapse. The regions may indicate
areas and sites suitable for the installation of specific types of PV systems and are forced to adapt their disciplines, in compliance with paragraph 10 of Article 12 of Legislative Decree 387/2003 as amended by the Finance Act 2008, within 90 days date of entry into force of the guidelines. If not implemented within this period, apply the national guidelines.